Planned Maintenance: File Storage Infrastructure Migration

Scheduled Maintenance Report for RIPE NCC

Completed

The scheduled maintenance has been completed.
Posted Sep 04, 2025 - 14:00 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 04, 2025 - 13:00 CEST

Scheduled

We will be performing a scheduled migration of our file storage infrastructure to a different data centre. This is part of our effort to reduce our data centre footprint and increase the geographical distance between our data centres.

During this maintenance window, the following services will be temporarily unavailable for approximately one hour: ftp.ripe.net, data.ris.ripe.net and data-store.ripe.net.
Posted Sep 02, 2025 - 17:00 CEST
This scheduled maintenance affected: Non-Critical Services (RIS (Routing Information Service), ftp.ripe.net).